Monday, 23 March 2009
Week 8 - Progress on the rear extension










As we now have 2 extensions, I will call them the rear and side extensions from now on. I wouldn't want you to get confused.
I know I keep saying this, but now you can see what it is going to look like. In these shots we have put real people in the shots (well Dudley, Steve and Damien anyway) to give you a sense of scale. Next week the glass may arrive...
Week 7 - Lots of other things happening..






The megaflow and boiler are installed, the plastering in the back moves on, the decorating continues in the front and to top the week... A rare photo of the Damien, caught here in classic pose with phone in ear. As soon as he saw us, he darted back into the shadows. Rumour has it that he is still pining over the loss of his Little Orange Digger.